Starbase Aerial Archive

Year: 2020


Subject: OLM


2020/12/16: OLM Legs Poured with Concrete


The OLM's six columns are all raised at this point, propped up by support structure.
Submitted 04/25/24

2020/9/24: OLM


Submitted 04/25/24

2020/9/12: Five OLM Leg Columns Installed + Rebar


Submitted 04/25/24

2020/8/27: OLM Leg Rebar Installation Progress


Submitted 04/25/24

2020/8/27: OLM Leg Casings Staged Before Installation


The first of six OLM leg casings was lifted into place before being poured with concrete. Note the 6-pointed stabilization structure.
Submitted 04/24/24

2020/8/20: OLM Leg Casing


The first OLM leg casing was lifted into place. 
Submitted 04/24/24

2020/8/20: OLM Leg Casing Part II


Submitted 04/24/24

2020/8/14: OLM Legs' Rebar Cages


The rebar for the pile cap for the first OLM was laid in early August 2020 and disintegrated in late April 2023. 
Submitted 04/24/24

2020/8/7: OLM Pile Cap Rebar


Submitted 04/24/24

2020/7/30: Closeup: OLM Foundations Poured with Concrete


Submitted 04/24/24

2020/7/20: OLM Rebar Foundations


The rebar to form two out of six legs of the OLM can also be seen. Little did we know, we would see this exact same rebar again in three years following the destruction of Flight 1.
Submitted 04/24/24

2020/7/14: OLM Foundation Rebar


Submitted 04/24/24

2020/7/5: OLM: Just a Dirt Circle For Now


Please ensure you are following the while using this archive.