Booster 11 and ship 29 getting ready for second wet dress rehearsal

2024/5/24: WDR #2 Preparations


After Starship's fantastic first flight, the rocket had done its damage to the pad. RGV was lucky enough to get out and peek through the clouds.

2023/4/20: IFT-1 First Look - OLM Damage


2022/5/13: OLM


2022/5/13: OLIT QD


2022/5/13: OLM


2022/5/13: Ship QD


2022/4/13: OLM with Booster 7


2022/4/6: OLM with B7 Atop It


2022/2/2: OLM and OLIT


2022/1/20: OLM and BQD, Part I


2022/1/20: OLM and BQD, Part II


The Chopstix have been installed.

2021/10/26: OLM Stix


Moving a little into the future, we have this picture from October 18th where the Chopsticks were integrated, they got installed two days later on October 20th

2021/10/18: OLM


2021/9/24: Booster 4 on OLM


2021/9/24: OLIT Chopsticks


2021/9/21: OLM, OLIT, B4


2021/9/9: B4 on the OLM


The QD Arm got lifted and installed onto the Tower, this was a big step towards completing the Tower Systems for full stack testing and future launches.

2021/9/3: OLM


The Claw. This is an early idea to help stabilise the full stack by attaching the Ship Quick Disconnect Arm to the Lifting Pins at the top of the Booster. It was only used couple of times and then it was removed.

2021/9/3: The Claw


2021/8/19: OLM and Tower


S20 on top left

2021/8/13: OLM Overhead


2021/8/13: OLM and S20


2021/8/4: B4 Lifted on OLM


2021/6/5: OLIT 4th Level


2021/6/5: OLM Elbow Joints


Was lifted the day before

2021/5/25: OLIT Section 2


2021/5/25: OLM Table


2021/5/25: OLM and OLIT Level 2


2021/5/21: OLIT First Segment


2021/4/21: OLIT First Level


OLM Area.
SN8 on the Landing Pad.

2021/1/1: OLM


2020/12/16: OLM Legs Poured with Concrete


The OLM's six columns are all raised at this point, propped up by support structure.
Submitted 04/25/24

2020/9/24: OLM


Submitted 04/25/24

2020/9/12: Five OLM Leg Columns Installed + Rebar


Submitted 04/25/24

2020/8/27: OLM Leg Rebar Installation Progress


Submitted 04/25/24

2020/8/27: OLM Leg Casings Staged Before Installation


The first of six OLM leg casings was lifted into place before being poured with concrete. Note the 6-pointed stabilization structure.
Submitted 04/24/24

2020/8/20: OLM Leg Casing


The first OLM leg casing was lifted into place. 
Submitted 04/24/24

2020/8/20: OLM Leg Casing Part II


Submitted 04/24/24

2020/8/14: OLM Legs' Rebar Cages


The rebar for the pile cap for the first OLM was laid in early August 2020 and disintegrated in late April 2023. 
Submitted 04/24/24

2020/8/7: OLM Pile Cap Rebar


Submitted 04/24/24

2020/7/30: Closeup: OLM Foundations Poured with Concrete


Submitted 04/24/24

2020/7/20: OLM Rebar Foundations


The rebar to form two out of six legs of the OLM can also be seen. Little did we know, we would see this exact same rebar again in three years following the destruction of Flight 1.
Submitted 04/24/24

2020/7/14: OLM Foundation Rebar


Submitted 04/24/24

2020/7/5: OLM: Just a Dirt Circle For Now